Bid price extremely low for the D1 highway

19. March 2017

The Office for the Protection of Competition ("OPC") recently found that part of the bid made by two construction companies to construct a section of the D1 highway was extremely low. The companies' winning bid had quoted a price of only CZK 1,- for the supply of software and computers to a roadside dispatch centre. Their total bid price, however, was 382 million crowns, which differed by only 1.5% from the second best bid. According to OPC, the pricing of items for only a few crowns may cause unfair competition, since this could disadvantage bidders which have taken into consideration all costs in their offer. OPC also held that there is a real risk that the company's services will not be of the required quality.